Before You Begin

Pre-Installation Checklist

Before beginning the installation of your machine, we recommend completing the following checklist.

Inspect Delivered Items

  • Inspect the item(s):

    • Photograph any damage that may have occurred during shipping.

    • Note any damage on the delivery receipt before signing for the shipment. If there is extensive visible damage to the machine, refuse to accept the shipment.

    • Verify the received goods against the packing list.

If there is any damage or shortages, you must contact Tormach within 30 days of receipt. Create a support ticket with Tormach Technical Support at tormach.com/how-to-submit-a-support-ticket for guidance on how to proceed.

  • If there are any items that have not yet been delivered, we recommend waiting until you've received all shipments to begin installing the machine. Depending on the product and options ordered, the system may arrive in one or more shipments of:

    • Accessories (if applicable)

    • Machine

NOTE: The machine system and large accessories are sent by freight carrier. Smaller accessories may be sent by parcel service.

Review Site Requirements

  • Verify that your shop meets the necessary space, electrical, and air requirements (refer to “Site Requirements”).

  • Verify that the temperature and humidity levels are within the machine’s operating requirements (40°F-90°F (5°C-32°C), 5%-95% humidity).

  • Verify the availability of the appropriate power for the machine and any accessories you plan to install, and ensure a certified electrician is available if needed.

  • Verify the availability of clean, dry air (90-120 psi (620-825 kPa)).

Prepare Your Shop Space

  • Verify that the area where the machine will be installed is clean, dry, and free of clutter.

  • Verify that the space has proper lighting and ventilation in accordance with the machine’s operating requirements.

  • Set up appropriate containers for packing materials, crates, and other waste generated during the unboxing and installation process to keep the work area clean and safe.

Gather Required Materials

  • Have Citgo EP Compound 220 Oil (PN 52499) or similar available.

  • Lay out all necessary tools, hardware, and materials in a convenient, accessible location near the installation site to prevent interruptions during the setup.

  • Have safety equipment available, including protective eyewear, closed-toed shoes, and gloves, as required during installation and initial operation.

Review Installation Materials

  • Before starting any installation tasks, read through the relevant procedures and safety precautions to better understand the steps and requirements.

  • Identify your setup or installation procedure depending on which machine configuration you purchased.

    • Self-Assembled Machine Follow the installation procedures in Self-Assembled Installation, go to Verify the Installation, and then, if applicable, go to Install Accessory Components.

    • Factory-Assembled Machine Follow the setup procedures in Factory-Assembled Machine Setup, go to Verify the Installation and then, if applicable, go to Install Accessory Components.

Installation Tools and Items

Before uncrating and beginning the initial setup of your machine, collect the following tools and items.

  • Assistant to help you

  • Cable ties

  • Cordless drill with a Phillips bit

  • Hammer

  • Machinist level

  • Metric hex wrench set

  • Open end wrench, 27 mm and 30 mm

  • Pallet jack

  • Phillips screwdriver

  • Pry bar

  • Safety eyewear that meets ANSI Z87+

  • Shears or knife

  • Socket set

  • Step ladder

  • Snips

  • Thread seal tape

  • Work gloves

Move the Pallet

Shipments arrive in crates loaded on pallets, which the freight carrier unloads onto the curb or loading dock.

WARNING! Transportation and Lift Hazard: Before moving the machine, you must confirm that all persons are clear of the area below the machine. Qualified professionals must transport, lift, and move the machine. Moving parts can entangle, pinch, or cut you, causing death or serious injury.

Verify that the ground surface is smooth and clean of debris, and then use a pallet jack to move the pallet(s) to the desired installation location. Follow the instructions on the pallet to determine from which side to lift.

NOTE: If the ground is not smooth, you may need to use a forklift (or similar lifting equipment rated for uneven surfaces) to move the pallet(s).

Looking for more information?

This is a section of the 1500MX operator's manual. To view the whole manual, go to Tormach document UM10811.

If you have additional questions, we can help. Create a support ticket with Tormach Technical Support at tormach.com/how-to-submit-a-support-ticket for guidance on how to proceed.

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.